Bund Lining Types

Bund Wall Lining

Bund wall lining is the chemically resistant, impermeable coating applied to the vertical faces of a bund wall, the engineered perimeter built around a tank, vessel or storage area. It works alongside bund floor lining and expansion joint detailing to form a continuous containment envelope that holds any escaped liquid safely.

Definition

What is Bund Wall Lining?

A bund wall is the concrete or masonry barrier built around a primary storage vessel to catch spills, leaks or overflows. Bund wall lining is the protective layer bonded to it, usually a multi coat resin system that makes the wall chemically resistant and impermeable. Untreated concrete is porous and degrades over time. Lined, the wall performs as part of a compliant containment system across its full design life.

When is Bund Wall Lining Required?

  • Bund wall lining is required wherever a vertical containment wall has to hold back liquid under hydrostatic load. Triggers that are wall-specific include splash exposure at tanker offloading, rainwater ingress at the top edge, efflorescence and carbonation on exposed faces, or any integrity test that questions a wall's stated capacity. New builds specify lining at construction, refurbishments usually follow a failed test.
  • This work falls under the regulations COMAH, the Oil Storage Regulations, Environment Agency PPGs and CIRIA C736.

Common Bund Wall Lining Structures

Concrete bunding walls surrounding bulk storage tanks

Bund walls for oil tanks and heating oil installations

Fuel tank bund walls at depots, generator compounds and standby plant

Reinforced concrete bund walls around process vessels

Masonry and blockwork bund walls at smaller facilities

Precast concrete bund wall panels

Dwarf walls around drum and IBC storage areas

Walls to tanker offloading and loading bays

Chemical dosing enclosure walls

Internal walls subdividing compartmented bunds

Pit and sump walls within process areas

Bund Wall Lining System Performance Requirements

  • Chemical resistance: it must resist the substances stored at realistic concentrations and temperatures, from acids and alkalis to solvents, hydrocarbons and process specific chemicals.
  • Impermeability: a continuous, pinhole free barrier, because a bund is only as good as its weakest detail.
  • Adhesion: it must bond to the concrete substrate and stay bonded through thermal cycling, hydrostatic loading and chemical attack.
  • Thickness: enough specified film build to resist permeation, mechanical damage and chemical degradation across the design life.
  • Durability: it must take incidental impact, cleaning regimes and, on external bunds, UV exposure.
  • Crack bridging: it should absorb minor substrate cracking without losing containment.
  • Vertical application: it must hold film thickness on vertical faces without slumping, sagging or thinning at arrises.
  • Fire performance: for hydrocarbon storage, fire resistance and low flame spread may be required.
Systems

Recommended Bund Wall Lining Systems

The right resin for a bund wall depends on chemistry, temperature and how the vertical face is loaded: splash exposure in normal operation, hydrostatic load when the bund holds a spill, and weathering at the top edge. We specify from a range of proven systems.

Epoxy Resins

A core material for vertical hydrocarbon and dilute chemical duty. Modern thixotropic epoxies build to film thickness on a vertical face without sag, suiting most bund walls for oil tanks where splash and intermittent hydrostatic loading dominate.

Polyurethane Resins

The natural choice for external bund walls. PU absorbs the movement between a sun warmed outer face and a cooler inner face, copes with rainwater at the top edge, and bridges the fine cracking that shows first along a wall's vertical run.

Polyurea Resins

Rapid cure systems that reline a full bund wall in one mobilisation, walked on within hours and back in service the same day. Their toughness suits walls taking impact from tanker arms, drum handling and forklifts at the base.

Vinyl Ester Resins

Specified where the wall sees concentrated acid splash during decanting, loading or transfer. Vinyl esters hold up at the upper inner face where standard epoxies blister or soften, and outperform across the splash zone of an acid bund wall.

Novolac Epoxy Resin

Uprated chemistry for hot solvent vapour, high concentration acid splash and elevated service temperatures. Specified where the inner wall face sits above a heated tank or meets aggressive vapour rising through the bund.

Methods

Recommended Bund Wall Build Up Methods

Vertical work has its own demands: film thickness without sag, top edge weathering, formwork defects in the concrete and access from MEWP or scaffold. Every method below is shaped around them.

Surface Preparation

Vertical prep differs from a floor on access, dust control and waste capture. We blast or grind from MEWP or scaffold, contain debris falling to the bund floor, and strip laitance, form release and carbonated layers before priming.

Lining and Levelling

Addressing the defects of poured concrete walls: honeycombing, blow holes, form release residue and tie marks. The face is made flat enough for a thixotropic film to build cleanly before the chemical resistant coats go on.

Protective Coatings

Multi coat systems applied with sag and lap line control in mind. We work top down to manage runs, hold film thickness evenly across the wall height, and feather laps so the inner face reads as one continuous coating from cove to crest.

Bund Lining Repairs

Wall-only remediation where the floor below is sound. Typical work includes reinstating splash-damaged upper inner faces, repairing weathered top-of-wall sections, and patching localised

Trowel Applied Mortar Systems

High build mortars used selectively: rebuilding spalled top of wall edges, repairing kicker damage at the base, and reinstating splash zones where tanker arm impact or chemical contact has eaten back the face.

Site Fabrication

For elements standard sections do not cover: fabricated top of wall caps, drip flashings, tank to wall interface plates at the vessel skirt, and bespoke profiles around steelwork and pipework that pierce the face.

Key Bund Wall Design and Detailing Considerations

  • Joints: construction, day and movement joints all need explicit treatment. See our Expansion Joint and Detail Treatment page.
  • Penetrations: pipework, supports, cable routes and drainage through the wall are leak paths unless sealed and engineered to the same standard as the main lining.
  • Corners: sharp internal corners are stress risers. Coved fillets at wall to floor and wall to wall intersections are standard practice.
  • Top-of-wall terminations: rainwater ingress, thermal stripping and mechanical damage all start at the top edge, so sealed, properly detailed terminations are essential.
  • Drainage: drains through a bund wall must be valved, normally closed and detailed so the lining stays continuous around every fitting.
  • Capacity and height: bund wall capacity, bund wall height and freeboard should give at least 110% of the largest primary vessel, plus rainfall and firefighting water. These figures drive the bund wall design and every bund wall drawing.
  • Surface preparation: the specified surface profile (typically ICRI CSP 3 to 5) is the foundation for adhesion; skimping here undoes every downstream decision.
Regulatory Compliance

Bund Wall Lining Regulatory Compliance

Bund wall lining sits within a broad UK regulatory framework, and the specification should evidence compliance from day one. The principal obligations are:

COMAH (Control of Major Accident Hazards Regulations): requires operators to prevent major accidents and limit their consequences. Environment Agency (EA): PPG2 (oil storage), PPG18 (chemicals) and sector specific guidance. HSE: workplace exposure, process safety, DSEAR and wider duty of care. Oil Storage Regulations: specific bund wall requirements for containment of oils and fuels above defined thresholds. CIRIA C736: practical industry guidance on bund wall construction and containment design.
See Our Standards & Regulations →
Get Independent Expert Advice

Get Independent Expert Advice

Speak to our technical specialists about your bund lining requirements. Free, no-obligation site surveys available nationwide.

FAQ

Bund Wall Lining FAQs

A correctly specified, properly applied and well-maintained bund wall lining typically delivers 15–25 years of compliant service across most UK industrial duties. Top-of-wall and splash-zone areas tend to sit at the lower end of that range, while the main vertical face often outlasts the surrounding asset infrastructure.

Our Work

Featured Case Studies

View all projects
Get Independent Expert Advice

Get Independent Expert Advice

Speak to our technical specialists about your bund lining requirements. Free, no-obligation site surveys available nationwide.